On October 28, 2025, the Board of Directors of DTE Energy Company ("DTE Energy") approved
execution of a Primary Supply Agreement ("PSA") and an Energy Storage Agreement ("ESA") between
DTE Energy's wholly-owned subsidiary DTE Electric Company ("DTE Electric") and Green Chile
Ventures LLC ("Customer") a wholly owned subsidiary of Oracle Corporation.
Under the terms of the PSA, DTE Electric will provide approximately 1.4 gigawatts of electric service to
Customer's future data center to be located in southeast Michigan ("Project"). The term of the PSA will
run through February 2045, with options to extend the term. The electric service will ramp over time,
expecting to achieve full delivery in December 2027. The PSA also establishes minimum monthly charges
and, if applicable, termination fees if the PSA terminates early.
Under the terms of the ESA, DTE Electric will, at Customer's cost, build and operate approximately 1.4
gigawatts of energy storage capacity to support its electric service to the Project. DTE Electric will
operate each energy storage facility for a period of 15 years, with options to extend upon mutual
agreement of Customer and DTE Electric. Customer's parent is providing credit support to DTE Electric
for both the PSA and ESA.